Hello GTD'ers,
In my Outlook/GTD system I've my projects, next actions etc.
If someone asks me for a new piece of work, I set it up as a GTD project and assign myself next actions etc.
Then another piece of work shows up and I do the same. If it's a deadline, the deadline is marked on the calendar, but not necessarily the time I'll need to complete the task beforehand.
I've now a list of various projects and actions, but what I'm finding is I have no idea of the total time required to complete my current workload before I commit to any new work.
Some items don't have hard landscape deadlines and what I'm finding is that these tend to hang around uncompleted as hard landscape items effectively take priority.
Also, when someone asks "when can this be completed by..." it's currently difficult to give an answer as I've no estimated times on the existing workload.
What I'd like is to look at my system and see I'm already committed with say 80 hours work over the next 2 weeks, so any additional work wouldn't be completed for at least 3 weeks.
This then has the option of saying, I can do this new work if say 10 hours of the current 2 week commitments slid back to 3 weeks.
My thoughts are:
* Hard landscape more on the calendar, even items without deadlines, set my own deadlines instead?
* Don't only hard landscape the deadline of a task to be completed on say Friday, but also hard landscape Tue and Wed with myself to complete the work ready for Friday. Currently I'm tending to put only the deadline date on there and not blocking out time with myself to complete the work. This is dangerous as the calendar fills up with deadlines with no time allocated to complete them.
* I could create a custom field in Outlook with an estimate of the time for the task/project. I could then write a macro/formula to total this in say task view. This would take into account due date and time estimated. I.e. 27 hours of tasks committed to complete by tomorrow = problem!
* I think the key to this could be hard landscaping with myself. Put almost the lot on the calendar and review that when new work requests come in. It's all very well for someone to ask for work with a "no rush, just whenever..." deadline - but then they might not get it for 6 months!
* I'm concerned that taking the above approach would put almost everything on the calendar and nothing on the next action lists - which goes against the fluid nature of GTD and back into a hard fixed schedule method? My calendar is where i'll be focusing on, currently it tends to be action lists.
Background to this, is I'm currently over worked - I've way more projects that can be completed in timeframes and my colleagues know this and appreciate the fact some items will be slip. However, it is only a temporary overload (yeah right!), and I'm looking at ways to managing it before being even more over committed.
Any ideas or feedback, very much appreciated.
Take care,
Andy D.
In my Outlook/GTD system I've my projects, next actions etc.
If someone asks me for a new piece of work, I set it up as a GTD project and assign myself next actions etc.
Then another piece of work shows up and I do the same. If it's a deadline, the deadline is marked on the calendar, but not necessarily the time I'll need to complete the task beforehand.
I've now a list of various projects and actions, but what I'm finding is I have no idea of the total time required to complete my current workload before I commit to any new work.
Some items don't have hard landscape deadlines and what I'm finding is that these tend to hang around uncompleted as hard landscape items effectively take priority.
Also, when someone asks "when can this be completed by..." it's currently difficult to give an answer as I've no estimated times on the existing workload.
What I'd like is to look at my system and see I'm already committed with say 80 hours work over the next 2 weeks, so any additional work wouldn't be completed for at least 3 weeks.
This then has the option of saying, I can do this new work if say 10 hours of the current 2 week commitments slid back to 3 weeks.
My thoughts are:
* Hard landscape more on the calendar, even items without deadlines, set my own deadlines instead?
* Don't only hard landscape the deadline of a task to be completed on say Friday, but also hard landscape Tue and Wed with myself to complete the work ready for Friday. Currently I'm tending to put only the deadline date on there and not blocking out time with myself to complete the work. This is dangerous as the calendar fills up with deadlines with no time allocated to complete them.
* I could create a custom field in Outlook with an estimate of the time for the task/project. I could then write a macro/formula to total this in say task view. This would take into account due date and time estimated. I.e. 27 hours of tasks committed to complete by tomorrow = problem!
* I think the key to this could be hard landscaping with myself. Put almost the lot on the calendar and review that when new work requests come in. It's all very well for someone to ask for work with a "no rush, just whenever..." deadline - but then they might not get it for 6 months!
* I'm concerned that taking the above approach would put almost everything on the calendar and nothing on the next action lists - which goes against the fluid nature of GTD and back into a hard fixed schedule method? My calendar is where i'll be focusing on, currently it tends to be action lists.
Background to this, is I'm currently over worked - I've way more projects that can be completed in timeframes and my colleagues know this and appreciate the fact some items will be slip. However, it is only a temporary overload (yeah right!), and I'm looking at ways to managing it before being even more over committed.
Any ideas or feedback, very much appreciated.
Take care,
Andy D.