Yes, the so called bookmarking method already mentioned by another poster in this thread.
What I was talking about however was the case in which no work is done on that project at all. This is different from the case in which a NA on a context list gets done and now that project lacks of an action reminder until the next weekly review.
The next weekly review comes into play, because that would be the guaranteed minimum point at which the project in question might receive more thorough organization. At that point the practitioner might decide that a single NA and a project plan isn't enough any more. Not because only at that point a subsequent NA would be added to the context lists.
What I was explaining in my post is that the root cause for "not engaging context lists", the stated problem in the OP, is not so much the wrong granularity of the formulation of the NA reminder, but a too lofty degree of project organization in the whole system.
Only if you are okay with not touching the respective "deep work" project for the time span determined as "at least to the next weekly review", is a single NA on a context list an appropriate level of organization for that project.
I feel that there's something going unstated. For example, is this a scenario where the project is represented by one and only one NA,
and there is no associated project plan or other support material? And so when the person realizes that the project didn't move that week, they decide that it needs a project plan?
This is just a guess. I'm fairly confused.
For me, an active project that doesn't get touched in a week is a project that, for whatever reason, (1) was not possible that week, or (2) dropped to a lower priority that week.
Random example for me:
Right now, in my off time, my top priority is gardening--I'm doing a fresh round of redesign of my garden. But we're in the middle of a hot summer, so my gardening time is limited--I need to drag myself out of bed early to get a couple of hours in before my workday starts, or, on the weekend, three or four hours before it just gets too hot.This means that I have active non-gardening projects because I just can't garden in the afternoon or evening.
But if we abruptly had a stretch of sub-eighty-degree days, I would leap on that opportunity and I would put those other projects aside. They wouldn't get touched for a week, but that wouldn't be because they only had one NA, or because i hadn't considered them deeply, but instead because they are a lower priority.
Equal and opposite, if we had several days of steady rain, it would be the garden projects that would move aside, but, again, not because they have only one NA and not due to insufficient deep thought or planning.
Now, the distinction here may be "active" projects. Most of my projects are in Someday/Maybe. If one is in my active list, that's either because (1) I firmly expect to work on it in the next week or (2) I've chosen it as a backup in case the "firmly expect" projects can't be done. So we might be talking about the same thing, except my deeper thought and planning happens before the project is ever promoted to "active" and before it ever gets an NA.