Hi all, just getting into GTD, a little confused about project-action list prioritization...
So, let's say I have (as David says) 50-100 projects I'm working on at any given time. And let's say that I've assigned a first action to each one of those projects. I also have maybe 50 one off actions (change lightbulb in bedroom etc.).
So now if I look at my actions list I have 150 things to do. Great.
BUT, not everything really has equal weight...
So, let's say I have a university assignment due in 3 weeks. On Sunday night I determined that my next action on that project is to contact my lecturer to clarify something I'm confused about. So Monday morning I contact my lecturer and get the answer to my question and tick that action off as completed.
Now I have 149 actions left on my list...great...except that I now have zero actions left on my "university assignment" project...
So...at what point do I review this for next actions? Because it makes little sense that I would be spending the rest of the week doing lots of other things when this is overall the most important.
Or, what if I spoke to my lecturer at 9am...there's still the whole day left, plenty of time left to do more actions on that project..at what time do I decide what those next actions are?
Am I meant to be reviewing my next actions on my project list daily? (as part of the 30-90min daily inbox clean)
I'm a little confused, please help! Thanks!
So, let's say I have (as David says) 50-100 projects I'm working on at any given time. And let's say that I've assigned a first action to each one of those projects. I also have maybe 50 one off actions (change lightbulb in bedroom etc.).
So now if I look at my actions list I have 150 things to do. Great.
BUT, not everything really has equal weight...
So, let's say I have a university assignment due in 3 weeks. On Sunday night I determined that my next action on that project is to contact my lecturer to clarify something I'm confused about. So Monday morning I contact my lecturer and get the answer to my question and tick that action off as completed.
Now I have 149 actions left on my list...great...except that I now have zero actions left on my "university assignment" project...
So...at what point do I review this for next actions? Because it makes little sense that I would be spending the rest of the week doing lots of other things when this is overall the most important.
Or, what if I spoke to my lecturer at 9am...there's still the whole day left, plenty of time left to do more actions on that project..at what time do I decide what those next actions are?
Am I meant to be reviewing my next actions on my project list daily? (as part of the 30-90min daily inbox clean)
I'm a little confused, please help! Thanks!